The timeline and deliverables for the process are as follows:
Timeline | Start | End | Status |
Kick off and Submission period | 11/05/2018 |
1/25/2019
25/01/2019 | In progress | ||
FBSC representatives and/or staff to send notice of opening of FY18 additional budget request process to RALOs | 26/11/2018 | 30/11/2018 | |
RALOs to review any ALS request or complete a template on behalf of the RALO and send requests to | 26/11/2018 | 04/01/2019 | |
Discussion of Proposals with Finance Staff and FBSC | 07/01/2019 | 11/01/2019 | |
Revised proposals to be sent to the FBSC for final review. | 14/01/2019 | 18/01/2019 | |
The ALAC to review the proposed At-Large FY20 ABRs during their monthly call | 22/01/2019 | 22/01/2019 | |
The FBSC to review all the RALO requests. | 23/01/2019 | 23/01/2019 | |
Submissions Due – send |
25/ |
01/2019 |
25/ |
01/2019 | On |
target |
Preliminary review of requests by ICANN.org |
28/ |
01/2019 |
08/ |
03/2019 | On |
target |
SO/AC consultations at ICANN 64 (by request, during Constituents’ Day) |
09/ |
03/2019 |
15/ |
03/2019 | On |
target |
Final assessments and recommendations |
by ICANN.org |
18/ |
03/2019 |
31/ |
03/2019 | On |
target |
ICANN Board Finance Committee Review and recommendation for approval to the Board |
15/ |
04/2019 |
19/ |
04/2019 | On |
target |
ICANN Board review and approval at May Board meeting |
22/ |
04/2019 |
03/ |
05/2019 | On |
target |
At-Large Requests
ALAC:
Request | Person or Group Submitting | Request Number | Description | FBSC Decision | Status |
---|---|---|---|---|---|
...