Item #Action Item DescriptionOwner/ResponsibleDue DateCompleted
 

Review Work Items

   
1

International Outreach Letter

 

Compile list and facilitate mailing

Provide digital signatures to staff

Translation into 5 UN languages

Lawrence Strickling, Jørgen Andersen

Staff/ATRT 2 Government Officials

Jørgen Andersen, Carlos Raul Gutierrez, Zhang Xinsheng

Staff/Translation Services

 

Draft completed, signatures provided

 

 

2Listing of questions for meetings with SO's, AC's and other groups in DurbanWork Stream Chairs28 June 
3Budget for ATRT 2Larisa GurnickASAP(tick)(Denise on 30 May)
4Accountability and Transparency Metrics Project information - scope, timing, etc.Denise MicheleASAP(tick)(Denise on 14 June)
5Review of Public Comments for possible case studies/research work by independent consultantsChair and Vice Chairs27 May(tick)(Chair and Vice Chairs)
6Provide feedback to staff regarding summary of Public CommentsChair and Vice Chairs  
7Create a sample Doodle Poll for voting on case studies/research work by independent consultantsAvri Doria (tick)(Avri on 24 May)
8Guidance re: update request from AFRINIC on progress and plans of ATRT2Chair and Vice Chairs (tick)(Brian on 30 May)
9Prepare Doodle Poll to collect ATRT 2 feedback on topics/case studies/areas of focus for potential Independent Consultant workBrian and staff (tick)(Doodle Polls launched 8 June, will close 11 June)
10Follow of up items from Coordination Call on 30 May - work with WS Chairs to a) refine list of issues; b) ensure documents provided by staff on the wiki are read/analyzed (including transcripts from May meeting in LA); c) develop timelines for substantive work between now and AugustChair and Vice Chairs  
11Provide WS Chairs with a listing of components that comprise the broadly-stated issues within each Work StreamLarisa Gurnick/staff (tick)(done for ICANN Finances- email 13 June; rest of issues pending prioritization by WS groups)
12Summary of public comments prepared by staff - review and approve for posting (http://mm.icann.org/pipermail/atrt2/2013/000478.html)ATRT 2 members20 June(tick)(done by staff on 20 June)
     
 

Administrative Items

   
AList of pen-holders for travel datesBrian Cute27 May(tick)(Chair and Vice Chairs on 30 May)
BArrange Australia meeting facilitiesAlice JansenASAP(tick)(Alice on 29 May)

C

Schedule full team meeting after 4 JulyAlice JansenASAP(tick)(Alice on 27 May)
DDraft invitation to SOs, ACs and other groups for meetings in DurbanAlice Jansen24 May(tick)(Alice on 24 May)
EFeedback on proposed schedule of calls for Work StreamsAlice Jansen, Work Stream ChairsASAP(tick)(Alice on 24 May)
FDraft reminder to individuals who did not complete interactive survey; compile email listCharla Shambley24 May(tick)(Charla on 24 May)
GSchedule a conference call with CSG in lieu of Durban meetingAlice Jansen Done
HProvide ATRT 2 with cost of Australia tripLarisa Gurnick (tick)(estimate provided via email to coordination list on 7 June )
IArrange for coordination calls to be recorded and summarizedAlice Jansen Done