The timing of GNSO Review activities has been adjusted to offer the GNSO community and leadership sufficient time to participate and provide their views.
Activities and Milestones | Dates | Completed |
---|---|---|
Provide update to the Structural Improvements Committee | 6 February 2015 | |
GNSO Review Working Party Meeting at ICANN52: | 11 February 2015 | |
GNSO Review Working Party working session discussion, Q&A with Westlake | 3 March 2015 | |
Deliver consolidated comments on Working Text to Westlake | 20 March 2015 | |
Westlake delivers Draft Report v.1 to GNSO Review Working Party, along with Westlake’s summary of disposition of comments and feedback from GNSO Review Working Party | 24 April 2015 | |
Provide update to the Structural Improvements Committee – Draft Report | 24-26 April 2015 | |
GNSO Review Working Party working session with Westlake | 4 May 2015 15:00-17:00 UTC | |
GNSO Review Working Party working session with Westlake (if needed) | 12 May 2015 19:00-20:30 UTC | |
Comments on Draft Report v.1 due from GNSO Review Working Party to Westlake | 15 May 2015 | |
Draft Report from Westlake posted for Public Comment (1 June posting deadline for ICANN53) | 1 June - 20 July 2015 | |
Provide update to the Structural Improvements Committee – Draft Report and Public Comments | 19 June 2015 | |
ICANN53 | 21 – 26 June 2015 | |
Community review of Report of Public Comments Received (following new Public Comment process) | 3 -17 August 2015 | |
GNSO Review Working Party working session with Westlake | TBD (during ICANN53) | |
GNSO Review Working Party working session with Westlake (if needed) | TBD (week of 27 July) | |
Final Report from Westlake distributed to the GNSO Review Working Party and the Structural Improvements Committee | 30 August 2015 |
GNSO Review Statistics | |
---|---|
360 Assessment: |
|
-- Main survey | 152 completed responses (250 started) |
-- Supplementary survey (WG) | 26 completed responses (50 started) |
Total | 178 completed responses |
| 60% completion rate |
Interviews: | 40 |
GNSO Review Working Party meetings: | 15 |
Engagement: |
|
-- Announcements page views | 1,709 |
-- Blog page views | 2,957 |
Outreach: |
|
-- Webinars | 3 |
-- Update presentations | 14 |
-- Blogs | 2 |
-- Videos | 2 |
-- FAQ Brochures and Post cards distributed | 3,000 |