Project Package
Date | File |
---|---|
31 Oct 2022 | TBD |
30 Sep 2022 | TPR_P1_Project_Package_20220930.pdf |
31 Aug 2022 | TPR_P1_Project_Package_20220831.pdf |
31 Jul 2022 | TPR_P1_Project_Package_20220731.pdf |
30 Jun 2022 | TPR_P1_Project_Package_20220630.pdf |
31 May 2022 | TPR_P1_Project_Package_20220531.pdf |
30 Apr 2022 | TPR_P1_Project_Package_20220430.pdf |
31 Mar 2022 | TPR_P1_Project_Package_20220331.pdf |
28 Feb 2022 | TPR_P1_Project_Package_20220228.pdf |
31 Jan 2022 | TPR_P1_Project_Package_20220131.pdf |
31 Dec 2021 | TPR_P1_Project_Package_20211231.pdf |
30 Nov 2021 | TPR_P1_Project_Package_20211130.pdf |
31 Oct 2021 | TPR_P1_Project_Package_20211031.pdf |
30 Sep 2021 | TPR_P1_Project_Package_20210930.pdf |
31 Aug 2021 | TPR_P1_Project_Package_20210831.pdf |
31 Jul 2021 | TPR-P1_Project-Package_20210731.pdf |
Baseline Project Plan: TPR_P1_Project_Plan_20210702.pdf
The proposed key milestone dates:
- 16 Jun 2022 – Deliver Phase 1A Initial Report on Transfer Policy for public comment, begin Phase 1B deliberations on Change of Registrant
- 14 Sep 2022 – Conclude review Phase 1A comments
- 30 Mar 2023 – Deliver Phase 1B Initial Report for public comment
- 28 Jun 2023 – Conclude review of Phase 1B public comments
- 16 Aug 2023 – Deliver Phase 1A, 1B Final Report to the GNSO Council
- Phase 2 is not in scope for this plan, but this process will be repeated when it begins.