  • 10 Org Recommendations Complete: 8.2 - 8.3.1 - 8.3.2 - 5.6 - 5.7 - 8.4.1 - 8.4.2 - 8.4.3 - 8.4.6 - 8.4.7 
  • 38 Org Recommendations in Progress: 1.1 - 1.6 -  1.7 - 1.8 - 3.1 - 4.1.4 - 5.1 - 5.11 - 6.1.7 - 6.3.6 - 7.1.1 - 7.2.1 - 7.2.2 - 7.3 - 8.1.1 through 8.1.15 - 8.1.17 through 8.1.21 - 8.3.3 - 8.4.4 - 8.4.5 - 8.4.8
  • 18 Org Recommendations not Started: 
    • 3 Preparing to begin implementation: 4.1.1 - 4.1.3 -  8.1.16 
    • 12 Requires completion of a given recommendation: 1.2 - 1.3 - 1.4 - 1.5 - 5.2 - 5.4 - 5.3 - 5.5 - 5.10 - 5.8 - 5.9 - 7.1.2
    • 2 Dependent on ongoing community initiative: 4.1.2 - 4.2 


OCT 2021


Progress in this Quarter


OCT 2021

FEB 2022

Improvement
COMPLETED810Completed implementation of an additional two recs. (8.4.1, 8.4.2)
STARTED3038

Started implementation on an additional ten recs. (1.1, 1.6, 1.7, 1,8, 3.1, 6.3.6, 7.2.1, 7.2.2, 7.3, 8.4.5)

NOT STARTED/ DEPENDENCIES2718Unlocked eleven recs.