Timeline for Draft Report (20 September 2013)

Friday, 27 SeptemberICC Conclusions

Sunday, 29 September

Assignments due – completed assessments and draft recommendations

Tuesday, 1 October - 13:00 UTC (4 hours)

ATRT 2 Full Team Call to review assessments and draft recommendations

Friday, 4 October

Draft Report circulated to ATRT 2 for review

Sunday, 6 October

ATRT 2 comments, edits provided to the ATRT2 list

Monday, 7 October

Draft Report provided to staff for translation with edits included

Friday, 11 October

Corrections in redline mode provided to staff for translation

Friday, 18 October

Publication of Draft Report