ATRT3 Implementation - Status of Recommendations

Complete (8)

Recommendation Components: 1.11.2, 2, 3.1, 3.23.3, 3.4, 5

In progress (7)

Recommendation Components: 3.5, 3.6, 4.1, 4.2, 4.3, 4.4, 4.5

Not started (0)

/


Quarterly Updates


Status
colourGrey
titleJun 2024

Image Added

Progress by Quarter


Status
colourGrey
titleAPR 2022

Status
titleJUN 2022

Status
titleSEPT 2022

Status
colourGrey
titleDEC 2022
Q4 2022

Status
titleMAR 2023
Q1 2023

Status
colourGrey
titleJun 2023
Q2 2023

Status
colourGrey
titleSEPT 23
Q3 2023

Status
colourGrey
titleDEC 23
Q4 2023

Status
colourGrey
titleMAR 24
Q1 2024

Status
colourGrey
titleJUn 24
Q2 2024

Complete1344444468
In progress14451011111197
Not started138

7

6100000



Rec #

Implementation Status

Priority level assigned by the community

(where P1 corresponds to the highest priority and P4 to the lowest - see here for more information)

Description

Notes

R1.1

Complete

P2

The Board approved five recommendations consisting of fifteen component parts as issued within the ATRT3 Final Report and specified in the Scorecard titled "ATRT3 Final Recommendations Board Action 30 November 2020." Further, the Board directed ICANN's President and CEO, or his designee(s), to take all actions directed to the ICANN org within that Scorecard, subject to the prioritization process.

The table below includes information relating to the implementation of Board approved recommendations.

Rec #

Status

Description

Implementation Update as of 17 February 2022

R1.1

Not started

To maximize the input from each Public Comment proceeding,

 ICANN org

 ICANN org shall update the requirements per the following:

- Clearly identify who the intended audience is.

- Provide a clear list of precise key questions in plain language that the public consultation is seeking answers to from its intended audience.

- Where appropriate and feasible, include translations of the summary, key questions, and responses.

- Include results of these questions in the staff report.

N/A

See implementation documentation.

R1.2

Complete

Not started

P2

With regards to other types of public

input ICANN org

input ICANN org shall:

- Develop and publish guidelines to assist in determining when a Public Comment process is required vs. alternate mechanisms for gathering input.

- Develop and publish guidelines for how alternative mechanisms for gathering input should operate, including producing final reports.

- Develop a system similar to and integrated with the Public Comment tracking system for all uses alternate mechanisms to gather input.

- Publish the complete “Public Comment Guidelines for

the ICANN Organization

the ICANN Organization.”

- Resolve the issue of blog posts collecting feedback information when the “Public Comment Guidelines for

the ICANN Organization”

the ICANN Organization” state that they “will not be used as mechanisms for collecting feedback.”

N/A

See implementation documentation.

R2

Complete

Not started

ICANN org

P4

ICANN org shall review the implementation of ATRT2 Recommendations in light of ATRT3’s assessment and complete their implementation subject to prioritization (see recommendation on the creation of a prioritization process).

N/A

See implementation documentation.

R3.1

Not started

Complete

P1

RDS Reviews:

- Given the final results of the EPDP process will certainly have an impact on any future RDS Reviews (and could even remove the need for any further Specific Reviews on this topic) and considering that ATRT3’s final report will be published prior to the EPDP delivering its final report, ATRT3 recommends suspending any further RDS Reviews until the next ATRT Review can consider the future of RDS Reviews in light of the final EPDP report recommendations, the results of the Board’s consideration of these, as well as any other developments which affect Directory Services.

N/A

See implementation documentation.

R3.2

Not started

Complete

P1

CCT Reviews

CCT Reviews

:

- There should be one additional and clearly

scoped CCT Review

scoped CCT Review.

- It shall start within the two years after the first introduction of the (possible) next round of new gTLDs to the root.

- It should be limited to a duration of one year.

- Additionally, a framework of data collection must be in place prior to the next round of gTLDs and the availability of all data sets should be confirmed prior to the selection of the review members and must be provided within 30 days of the review being launched.

N/A

See implementation documentation.

R3.3

Not started

Complete

N/A

SSR Reviews:

- Given SSR2 will not be finalized prior to ATRT3 completing its work, ATRT3 recommends that SSR Reviews shall be suspended until the next ATRT Review (or any type of review that include current ATRT duties) which shall decide if these should be terminated, amended, or kept as is.

- This review could be re-activated at any time by

the ICANN Board

the ICANN Board should there be a need for this.

N/A

See implementation documentation.

R3.4

Not started

Complete

P1

ATRT Reviews:

ATRT Reviews should continue essentially as they are currently constituted but with the following enhancements:

- Shall start no later than two years after the approval by the Board of the first recommendation of the Holistic Review.

- Shall maintain responsibility to recommend to the Board the termination or amendment of other periodic reviews and the creation of additional periodic reviews (including reassessing reviews terminated by previous ATRTs).

- All pre-identified documentation that is required for the review, such as the previous ATRT’s implementation report, shall be available at the first meeting of the review team.

- Terms of reference shall be established at the first meeting.

- Note: The Operating Standards for Specific Reviews shall be amended to allow review teams to obtain professional services, which are not covered by subject matter experts, should they require such services.

N/A

See implementation documentation.

R3.5

In progress

Not started

P1

A new Holistic Review

of ICANN shall

of ICANN shall be set up:

Timing considerations:

- The first one shall start no later than one year after approval by the Board of the first recommendation by ATRT3.

- The next Holistic Review shall start no later than every two-and a-half years after approval by the Board of the first recommendation of the latest ATRT Review[...].

- The launching of any other review activities should be suspended while a Holistic Review is active.

- Should operate based on Operating Standards for Specific Reviews and should be time limited to a maximum of 18 months.

Objectives:

- Review continuous improvement efforts

of SO

of SO/AC/NC based on good practices.

- Review the effectiveness of the various inter-SO/AC/NC collaboration mechanisms.

- Review the accountability

of SO

of SO/ACs [...].

-

Review SO

Review SO/AC/NC as a whole to determine if they continue to have a purpose [...], or if any changes in structures and operations are desirable [...].

N/A

R3.6

Not started

In progress

P2

Organizational Reviews:

Board

and ICANN org

and ICANN org shall evolve the content of Organizational Reviews into continuous improvement programs in

each SO

each SO/AC/NC:

Continuous Improvement Program:

-

 ICANN org

 ICANN org shall work with

each SO

each SO/AC/NC to establish a continuous improvement program. [...]

These continuous improvement programs will include:

Annual satisfaction survey of members/participants [...]

Regular assessment of continuous improvement programs: [...]

- The Board should publish at least every three years a summary of its continuous improvements over that period. [...]

- This continuous improvement program is not meant to be a cost reduction activity vs current overall costs of Organizational Reviews over a 5-year period. [...]

- Regardless of the processes selected by the

specific SO

specific SO/AC/NC, this shall fit in the financial constraints available for such activities.

N/A

R4.1

In progress

Not started

ICANN org

P2

ICANN org in strategic plans and operational plans shall provide a clear and concise rationale in plain language explaining how each goal, outcome, and operating initiative is critical to achieving the results of the one it is supporting (e.g., For each strategic goal there must be a rationale as to how it is critical for its strategic objective).

N/A

R4.2

In progress

Not started

ICANN org

P2

ICANN org in its strategic plans and operational plans shall have a clearly articulated, in plain language, specific criteria defining success which shall be S.M.A.R.T (unless appropriately justified) for all goals (strategic or not), outcomes (targeted or not), operating initiatives, etc.

N/A

R4.3

Not started

In progress

P2

For the FY2021- 2025 Strategic Plan and FY2021 Operating Plan,

 ICANN org

 ICANN org shall, within six months of approving this recommendation, produce a supplementary document using the criteria defining success in reporting on the progress of any relevant goal, outcome, operating initiative, etc. to create a listing of required rationales and specific criteria defining success (as defined by ATRT3 in this recommendation) for each goal (strategic or not), outcome (targeted or not), operating initiatives, etc. that are found in both of these documents and post it for public consultation prior to finalization. Once

finalized ICANN org

finalized ICANN org will append these to the FY2021-2025 Strategic Plan and FY2021 Operating Plan and use the criteria defining success in all reporting on the progress of any relevant goal, outcome, operating initiative, etc.

N/A

R4.4

Not started

ICANN org

In progress

P2

ICANN org shall publish an annual status report on all Strategic Plan and Operating Plan goals, outcomes and operating initiatives. This should clearly assess each of the elements presented in the Strategic and Operating Plans (goals, outcomes etc.) clearly indicating what progress was made vs the target in concise and plain language. Prior to being finalized the report will be submitted for Public Comment.

N/A

R4.5

In progress

Not started

ICANN org

P2

ICANN org shall publish an overarching report at the conclusion of a strategic plan starting with the 2016-2020 Strategic Plan. This should clearly assess each of the elements presented in the strategic plan; its text (objectives, goals, outcomes) clearly indicate if it was attained or not and justify that assessment in concise and plain language. The report shall conclude with a section distilling the results of the assessments and how this could be applied to following strategic plans or their revisions. Prior to being finalized the report will be submitted for Public Comment.

N/A

R5

Complete

In progress

Prioritized

ATRT3 recommends the following guidance

for ICANN org

for ICANN org in the creation of a community-led entity tasked with operating a prioritization process for recommendations made by review teams, cross-community groups, or any other community related budgetary elements the Board

or ICANN org

or ICANN org feels appropriate:

ATRT3 recommends that

all SO

all SO/ACs should have the option of participating in this annual process. [...]The Board shall also take into account the following high-level guidance for the prioritization process:

- Shall operate by consensus [...].

- Is meant to have a continuous dialogue [...].

- Shall consider WS2 recommendations [...].

- Must be conducted in an open, accountable, and transparent fashion [...].

- Shall integrate into the standard Operating and Financial Plan processes.

- Can prioritize multi-year implementations, but these will be subject to annual re-evaluation to ensure they still meet their implementation objectives and the needs of the community.

- Shall consider the following elements when prioritizing recommendations:

- Relevance

to ICANN’s

to ICANN’s mission, commitments, core values, and strategic objectives.

- Value and impact of implementation.

- Cost of implementation and budget availability.

- Complexity and time to implement.

- Prerequisites and dependencies with other recommendations.

- Relevant information from Implementation Shepherds (or equivalents).

The Board acknowledged that the implementation of this recommendation is dependent upon the need to prioritize all of ICANN's work through the annual planning cycle, and the need for the development of a framework in collaboration with the community and ICANN org. During FY21, ICANN org launched the Planning Prioritization Framework project with the intent to run a pilot focusing on the prioritization of recommendations resulting from specific reviews. While the Planning Prioritization Framework is comprehensive and includes all works/projects of ICANN, a subset of this framework will contribute to the design implementation phase of the Board-approved recommendation 5 of ATRT3 on prioritization of community recommendations