Category 1 = Low Needs2 =Medium Needs3 = High Needs | Task Descriptions | Task Type | Risk Level 1 = Low2 = Medium3 = High | Penholder(s) | Progress | Start | No. Week | ||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1 | Implementation development | Goal | Maureen Hilyard | 17%
| 28/08/2018 | 17 | |||||||
2. Meetings | Implementation Activity | ||||||||||||
31. ARIWG formed and has met | Implementation Activity | 1 | Maureen Hilyard | 100%
| 28/08/2018 | 1 | |||||||
4. Introduction completed | Milestone | Maureen Hilyard | |||||||||||
52. Quality advice #1 | Implementation Activity | 1 | Jonathan Zuck and Marita Moll | 0%
| 28/08/2018 | 17 | |||||||
63. Leadership team #4 | Implementation Activity | 1 | Maureen Hilyard and Hadia Elminiawi | 0%
| 28/08/2018 | 17 | |||||||
74. Working groups #7 | Implementation Activity | 1 | Javier Rúa-Jovet and Ricardo Holmquist | 0%
| 28/08/2018 | 17 | |||||||
85. Metrics #16 | Implementation Activity | 1 | Dev Anand Teelucksingh and Joanna SKulesza | 0%
| 28/08/2018 | 17 | |||||||
9. Category 1 completed | Milestone | ||||||||||||
2 | |||||||||||||