From the Bylaw Section 4.6:

(A)Each Supporting Organization and Advisory Committee participating in the applicable review may nominate up to seven prospective members for the review team;

(B)Any Supporting Organization or Advisory Committee nominating at least one, two or three prospective review team members shall be entitled to have those one, two or three nominees selected as members to the review team, so long as the nominees meet any applicable criteria for service on the team; and

(C)If any Supporting Organization or Advisory Committee has not nominated at least three prospective review team members, the Chairs of the Supporting Organizations and Advisory Committees shall be responsible for the determination of whether all 21 SO/AC member seats shall be filled and, if so, how the seats should be allocated from among those nominated.

...

Candidates

TBD


...

SSC Selection Process Timeline

DateStep
19 June 2024Expressions of Interest deadline
20 June 2024EOIs received by Standing Selection Committee (SSC)
20 June - 03 July 2024SSC will review the applications received and rank these taking into account the skills and experience required
08 July 2024The SSC will submit its recommendation to the GNSO Council in the form of a motion for confirmation of GNSO Liaison to the GAC to the GNSO Council
18 July 2024Consideration of motion and approval of candidates by GNSO Council during GNSO Council meeting

Overall PHR Timeline

Steps

Start Date

End Date

Duration

Call for Volunteers - window for applications to be submitted 

23 May

19 June

4 weeks

SO/AC’s review list of applicants and determine their respective nominations

20 June

 2 Aug

6 weeks

ICANN org posts a list of all SO/AC nominated applicants on the PHR wiki and produces a skill and diversity analysis of nominated candidates

 5 Aug

9 Aug

5 days

SO/AC Chairs select review team members and identify review leadership from list of nominated applicants

12 Aug

6 Sept

4 weeks

SO/AC Chairs inform ICANN of selected review team members.

9 Sept

9 Sept


Review team members are announced publicly

13 Sept