Item # | Category | Source of Request | Date of Request | Action Item Request | Action Owner | Anticipated Completion Date* | Progress Notes |
---|---|---|---|---|---|---|---|
494 | General | 129 | 19 November 2020 | Team members to resolve assignments in the list of Heather’s outstanding questions regarding Appendix D: Findings related to SSR1 recommendations | RT | 3 December 2020 | |
493 | General | 129 | 19 November 2020 | ICANN org to make the 10th December meeting a two-hour call, 15:00 – 17:00 UTC. | ICANN org | 26 November 2020 | |
492 | General | 129 | 19 November 2020 | Heather to use the time from Monday 23rd November – Monday 7th December to compile the report to be shared with the team on Monday 7th December. | Heather | 7 December 2020 | |
491 | General | 129 | 19 November 2020 | KC and Laurin will make the adjustments to the text as discussed on the plenary call today and hand off the document to Heather on Monday 23rd November. | KC and Laurin | 23 November 2020 | |
490 | General | 127 | 5 November 2020 | Heather to reach out to the original authors of the SSR1 text to ask for review of the proposed text additions to Appendix D. | Heather | 12 Novermber 2020 | |
489 | General | 127 | 5 November 2020 | Abuse subteam to suggest additional text to incorporate more context and explanations around the points that Danko raised in the document and as discussed on the call. | Abuse subteam | 19 November 2020 | |
488 | General | 126 | 29 October 2020 | Team members should make comments in the abuse document ahead of the team’s next call on 5 November. | RT | 5 November 2020 | |
487 | General | 126 | 29 October 2020 | Brenda to update calendar invites to reflect the revised meeting time. | Brenda | 5 November 2020 | |
486 | General | 123 | 1 October 2020 | Team members to review slides and share any comments via email by Monday 5 October. | RT | 5 October 2020 | |
485 | General | 123 | 1 October 2020 | Recommendation 29: KC to respond on list to Kerry-Ann’s email per the discussion on the call today. | KC | 8 October 2020 | |
484 | General | 123 | 1 October 2020 | Recommendation 28: Russ will share his notes with Naveed on the discussion on recommendation 28. Naveed to make adjustments to the text on 28 based on the notes. | Russ & Naveed | 8 October 2020 | |
483 | General | 123 | 1 October 2020 | Recommendation 26: Heather will adjust text based on Žarko’s proposal and send to Žarko and Boban for review. | Heather | 8 October 2020 | |
482 | General | 123 | 1 October 2020 | Recommendation 23: Heather will adjust text based on Žarko’s proposal and send to Žarko for review. | Heather | 8 October 2020 | |
481 | General | 122 | 23 September 2020 | SSR2 members to review and share any comments on the proposal for recommendation 29 in the document hereahead of next week’s meeting. | RT | 1 October 2020 | |
479 | General | 122 | 23 September 2020 | Eric to fill in the response column in the spreadsheet here for recommendation 21 where commenters support to say ‘noted’ or ‘thanks’. | Eric | 1 October 2020 | |
478 | General | 121 | 16 September 2020 | Heather to continue review of the document based on the input received. | Heather | 23 September 2020 | |
477 | General | 121 | 16 September 2020 | Heather to work with KC and Denise on merging Section 3.3 and 3.4. | Heather | 23 September 2020 | |
476 | General | 121 | 16 September 2020 | Review team members to raise any concerns on the risk subteam updates via the mailing list. | RT | 23 September 2020 | |
475 | General | 121 | 16 September 2020 | KC to share the document via email and receive input from review team members. | KC | 23 September 2020 | |
472 | General | 120 | 19 Aug 2020 | Alain to contact Zarko regarding how to move forward with recommendation 23. | Alain | 26 July 2020 | |
468 | General | 117 | 8 July 2020 | Staff to find out the process and timeline for next steps on the NCAP study, if ICANN org plans to publish a view on the report, and if so, when? | ICANN org | 15 July 2020 | |
452 | General | 110 | 20 May 2020 | Review team members to continue to work in subgroups and update the bar chart as work progresses. | Review Team | 1 July 2020 | |
442 | General | 107 | 8 Apr 2020 | KC to share proposed text that she believes should be included in the report with regard to prioritization, as articulated on the call. | KC | 15 Apr 2020 |
...