Background Information

22 April 2014, a Request for Proposals was issued to find an independent examiner for the GNSO Review 2014. 

Key Dates

The key dates identified for the Independent Examiner is: 

ActivityDates
RFP published22-Apr-14
Participants to indicate interest in submitting RFP30-Apr
Participant proposals due by13-May
Target for participant presentations (finalists)Week of 19 May (May 19-23)
Target for Final evaluations and selection of vendor (includes contracting and award to participant)10-Jun
Board appointment of independent reviewer26-Jun
Estimated start of implementation1-Jul
Final Report15-Jan-15

Key Documents