You are viewing an old version of this page. View the current version.

Compare with Current View Page History

« Previous Version 10 Next »

Category

1 = Low Needs
2 =Medium Needs
3 = High Needs
Task DescriptionsTask Type

Risk Level

1 = Low
2 = Medium
3 = High


Penholder(s)ProgressStartNo. Week
1

Implementation Development

Goal
Maureen Hilyard

17%

IN PROGRESS

28/08/201817

MeetingsImplementation Activity





1. ARIWG formed and has met; project introduced.Implementation Activity1Maureen Hilyard

100%

COMPLETED

28/08/20181

Introduction completedMilestone





2. Quality advice #1Implementation Activity1Jonathan Zuck and Marita Moll

0%

TO START

28/08/201817

3. Leadership team #4Implementation Activity1Maureen Hilyard and Hadia Elminiawi

0%

TO START

28/08/201817

4. Working groups #7Implementation Activity1Javier Rúa-Jovet and Ricardo Holmquist

0%

TO START

28/08/201817

5. Metrics #16Implementation Activity1Dev Anand Teelucksingh and Joanna Kulesza

0%

TO START

28/08/201817

Category 1 completedMilestone












2

1.Social media training #9








2. At-Large vs ICANN Outreach and Engagement #5






3. RALOs at Regional Events





















































  • No labels