The timing of GNSO Review activities has been adjusted to offer the GNSO community and leadership sufficient time to participate and provide their views.

Activities and Milestones

Dates

Completed

Provide update to the Structural Improvements Committee

6 February 2015

  •  

GNSO Review Working Party Meeting at ICANN52:
Westlake (independent examiner) briefing and presentation of Working Text

11 February 2015
10:30 am–Noon SGT
(Room: Butterworth)

  •  

GNSO Review Working Party working session discussion, Q&A with Westlake

3 March 2015
20:00-21:30 UTC

  •  

Deliver consolidated comments on Working Text to Westlake

20 March 2015

  •  
Westlake delivers Draft Report v.1 to GNSO Review Working Party, along with Westlake’s summary of disposition of comments and feedback from GNSO Review Working Party24 April 2015
  •  

Provide update to the Structural Improvements Committee – Draft Report

24-26 April 2015

  •  
GNSO Review Working Party working session with Westlake4 May 2015
15:00-17:00 UTC 
  •  
GNSO Review Working Party working session with Westlake (if needed)12 May 2015
19:00-20:30 UTC 
  •  
Comments on Draft Report v.1 due from GNSO Review Working Party to Westlake15 May 2015
  •  

Draft Report from Westlake posted for Public Comment (1 June posting deadline for ICANN53)

1 June - 24 July 2015

  •  
Provide update to the Structural Improvements Committee – Draft Report and Public Comments19 June 2015
  •  

ICANN53

21 – 26 June 2015

  •  
GNSO Review Working Party working session with Westlake

30 July 2015
19:00-20:00 UTC

To be rescheduled in September 

  •  

Community review of Report of Public Comments Received (following new Public Comment process)

14-28 August 2015

  •  

Final Report from Westlake distributed to the GNSO Review Working Party and the Structural Improvements Committee

31 August 2015 (approximately)

  •  
GNSO Review Working Party working sessionTo be scheduled
  •  
Organizational Effectiveness Community considers feasibility assessment and makes recommendation to the Board16 October
  •  
ICANN Board Action on Final ReportFebruary 2016 (date to be determined)
  •  


GNSO Review Statistics

360 Assessment:

 

-- Main survey

152 completed responses (250 started)

-- Supplementary survey (WG)

26 completed responses (50 started)

Total

178 completed responses

 

60% completion rate

Interviews:

40

GNSO Review Working Party meetings:

15

Engagement:

 

-- Announcements page views

1,709

-- Blog page views

2,957

Outreach:

 

-- Webinars

3

-- Update presentations

14

-- Blogs

2

-- Videos

2

-- FAQ Brochures and Post cards distributed

3,000


  • No labels