Suggested timetable for gTLD RG during the Application Comment Period
The new gTLD Review Group (gTLD RG) agreed to the revised timetable
Date | Activity |
---|---|
June 13 | Reveal Day - start of 60 day Application Comment Period (ACP) |
until end of July 26 | get comments from At-Large on the At-Large new gTLD Applications Dashboard Workspace (this would be Figure 2 of the Procedure to submit comments on and file objections to new gTLDs ) |
July 26 - July 27 | gTLD RG would review comments on the At-Large new gTLD Applications Dashboard Workspace and decide whether to draft formal comments (this would be Figure 3 of the Procedure to submit comments on and file objections to new gTLDs ) |
July 26 - August 2 | draft of formal comment posted on At-Large new gTLD Applications Dashboard Workspace and worked on by gTLD RG (this would be Figure 4 of the Procedure to submit comments on and file objections to new gTLDs ) |
August 2 to August 10 | final comment posted by gTLD RG on August 3 for ALAC's approval (this would be Figure 5 of the Procedure to submit comments on and file objections to new gTLDs ) |
August 12 | ACP ends |
June 13 - Reveal day - start of ACP Figure 2 - to the end of July 26 - get comments from At-Large on the wiki Figure 3 - July 26 - July 27 - this is when the RG would review comments on the wiki and decide to draft formal comments Figure 4 - July 26 - Aug 2 - draft of formal comment posted and worked on by RG Figure 5 - Aug 3 - Aug 10 - final comment posted on August 3 for ALAC to approve by August 10 Aug 12 - ACP ends