Comment: Migrated to Confluence 4.0

...

Directs staff to adopt as a working plan the Launch Scenario with launch date of Q2 2011, as contained in the graphic referenced.

Text

Wiki Markup*{_}RESOLVED{_}* _(2010.10.28.17), the Board directs staff to adopt as a working plan the Launch Scenario with launch date of Q2 2011, as contained in the graphic attached_ [here|http://www.icann.org/en/topics/new-gtlds/new-gtld-work-plan-28oct10-en.pdf] _\ here [PDF, 112 KB\]._

Implementation Actions

  • Adopt and implement Work Plan
    • Responsible entity: Services Staff
    • Due date: 9 Nov 2010 for posting Proposed Final Applicant Guidebook; 10 Dec 2010 for Board approval of Guidebook