Item #Source of RequestDate of RequestAction Item RequestAction OwnerAnticipated Completion Date
45Plenary call #1026 May 2022

Pilot Holistic Review ToR Team to continue to work on the ToR definitions over the next week

Pilot HR ToR team members2 June 2022
46Plenary call #1026 May 2022Investigate alternative times to the 9 June plenary call to increase potential attendanceICANN org2 June 2022








COMPLETED ACTIONS/REQUESTS


Item #Source of RequestDate of RequestAction Item RequestAction Owner

Anticipated Completion Date

Completed ResponseCompletion Date
1Coordination call #123 March 2022Establish a wiki space for the Pilot Holistic ToR teamwork.ICANN org31 March 2022Wiki space created.29 March 2022
2Coordination call #123 March 2022Revise the meeting invites to RSA's Zoom room and setup for observers.ICANN org31 March 2022The Coordination Group agreed to keep the existing format until a need arises to switch to a different format resulting from observer participation.31 March 2022
3Coordination call #123 March 2022Setup Skype chat groups for the General Pilot Holistic Review ToR team communications.ICANN org25 March 2022Skype chat groups created.25 March 2022
4Coordination call #123 March 2022Establish a working General Pilot Holistic Review ToR Google document for commenting and editing.ICANN org31 March 2022Google document create.28 March 2022
5Coordination call #123 March 2022Notify Herb Wayne (Ombudsman) of the General Pilot Holistic Review team meetings.ICANN org31 March 2022Ombudsman notified of meetings.31 March 2022
6Plenary call #125 March 2022Send Skype chat group invites to the General Pilot Holistic Review ToR Team.ICANN org31 March 2022Skype chat invitations sent.6 April 2022
7Plenary call #125 March 2022Send invites for the ToR Google document to the General Pilot Holistic Review ToR Team so they can provide comments.ICANN org31 March 2022Invites to ToR Google document sent.31 March 2022
8Plenary call #125 March 2022Avri Doria to draft blog post about Pilot Holistic Review. Avri Doria with support from ICANN org31 March 2022Draft blog post created.30 March 2022
9Coordination call #225 March 2022Create running list of action items for Pilot Holistic Review ToR Team.ICANN org31 March 2022Running list of action items created.30 March 2022
10Plenary call #231 March 2022Corrections to be made to ToR document as per 25 March meeting comments.ICANN org31 March 2022Corrections made to ToR document.31 M 2022
11Plenary call #231 March 2022Meeting for week of 4 April to be rescheduled, with invites to be sent thereafter.ICANN org5 April 2022Meeting scheduled for 7 April 2022, at 18:30 UTC, invites sent.7 April 2022
12Plenary call #231 March 2022Potential Pilot Holistic Review ToR Team meeting at ICANN 74 to be discussed during coordination meeting.Team leadsLeads31 March 2022Because the ICANN 74 meeting is focused on Policy, the Coordination Group decided it could be more appropriate to engage with the community via a webinar outside of ICANN 74, and will review this matter at the next meeting with the ToR team.31 March 2022
13Plenary call #231 March 2022Addition of 30 minutes to weekly meetings to be discussed during coordination meeting.Team leadsLeads31 March 2022The Coordination group agreed to add 30 minutes to weekly meetings moving forward.31 March 2022
14Coordination call #331 March 2022Update Pilot Holistic Review ToR Team meeting invitations to reflect addition of 30 minutes.ICANN org5 April 2022Future meeting invitations to include additional 30 minutes.31 March 2022
15Coordination call #331 March 2022Categorize comments in ToR document by color coding them to help guide and focus discussions.ICANN org7 April 2022Comments categorized by color in ToR document.5 April 2022
16Coordination call #47 April 2022Coordination Group to review and approve the outstanding meeting reports so they can be posted to the wiki space.Team leadsLeads14 April 2022Coordination Group approved reports.10 April 2022
19Plenary call #37 April 2022Coordinate future Pilot Holistic Review meeting dates/times with At-Large.ICANN org14 April 2022At-Large now being consulted for meeting scheduling.8 April 2022
20Plenary call #37 April 2022Coordinate future Pilot Holistic Review meeting dates/times with Board Ops due to scheduling conflicts.ICANN org14 April 2022Board Ops is actively consulted for meeting scheduling.8 April 2022
18Plenary call #37 April 2022Further discuss and decide on Pilot Holistic Review ToR Meeting at ICANN 74.ICANN org14 April 2022The group decided not to pursue a meeting at ICANN 74, expressing a preference for discussing the Pilot Holistic Review ToR using another format, such as a webinar.21 April 2022
21Plenary call #414 April 2022Move deliverables 1 and 2  into more appropriate sections within the ToR document.ICANN org21 April 2022Deliverable 1 was moved to prework section of deliverables. Deliverable 2 was moved to the decision-making and methodologies section of ToR.19 April 2022
22Plenary call #414 April 2022Insert the “good practices” definition into the definition section of the document.ICANN org21 April 2022"Good practices" was added to the definition section of the ToR.19 April 2022
24Plenary call #414 April 2022Find a way to display annotated text of the ToR in a more readable manner.ICANN org21 April 2022Accessibility feature in iOS is being used to enlarge text for viewing during Zoom calls.20 April 2022
17Plenary call #37 April 2022Create a roadmap for the Pilot Holistic Review showing milestones, prework, review work (within the 18-month timeframe), and postwork.ICANN org21 April 2022Initial concept Roadmap created and shared with Team leads in preparation for 28 April presentation.27 April 2022
25Plenary call #521 April 2022Compile new ToR draft comments into a document and circulate via email prior to next plenary call.ICANN org27 April 2022All comments 21 April Plenary Call comments from video and chat were recorded into a single documents and sent to all ToR Team members.27 April 2022
27Plenary call #521 April 2022Overview of Pilot Holistic Review Roadmap to be given during the 28 April plenary call.ICANN org28 April 2022Initial concept of Pilot Holistic Review Roadmap was presented during Plenary Meeting #6.28 April 2022
29Plenary call #628 April 2022Revise Pilot Holistic Review Roadmap based on feedback from the 28 April plenary call.ICANN org5 May 2022Pilot Holistic Review Roadmap revised as per 28 April Plenary Meeting feedback.3 May 2022
31Coordination call #628 April 2022Create Google doc to facilitate defining ToR terminology and send to Pilot Holistic Review ToR Team.ICANN org4 May 2022Google doc created and sent to Pilot Holistic Review ToR Team.3 May 2022
34Plenary call #75 May 2022Look at ICANN resources including Cross Community Working Groups to inform defining consensus and public comment.ICANN org12 May 2022ICANN definitions were identified and added to the definitions document. 11 May 2022
36Coordination call #75 MayAggregate unaddressed comments from the Deliverable and Objective sections of the ToR to focus 12 May discussions.ICANN org12 May 2022Unaddressed comments for the Deliverable and Comments sections were aggregated for discussion.10 May 2022
26Plenary call #521 April 2022Coordination Group to define “good practice” in the definition section of the ToR.Team leadsLeads28 April 2022Good practice has been defined. 12 May 2022
28Plenary call #628 April 2022Revise ToR objective C based on comments from the ToR Team to clearly articulate its intended purpose.ICANN org12 May 2022A thought paper was written to deconstruct objective C based on ToR team comments. 12 May 2022
33Plenary call #75 May 2022Schedule 2 June and 9 June meetings for the Pilot Holistic Review ToR Team.ICANN org5 May 20222 June and 9 June meetings have been scheduled and invitations have been sent. 12 May 2022
35Coordination call #75 May 2022Develop paragraphs to accompany definitions that require additional context in the ToR.ICANN org19 May 2022Paragraphs have been drafted and added to definitions.17 May 2022
32Plenary call #75 May 2022Update the Pilot Holistic Review Roadmap to reflect immoveable milestones (socialization, public comment, published deliverables).ICANN org12 May 2022The Pilot Holistic Review Roadmap has been updated with "immoveable" milestones. 19 May 2022
23Plenary call #414 April 2022Pilot HR ToR team members to use their email list to exchange ideas for how a list of evidence-based findings should be socialized and discuss at the next meeting.Pilot HR ToR team Team members21 April 2022Ideas for how evidence-based findings should be socialized have been discussed during the 12 May Plenary Meeting. 12 May 2022
36Plenary call #812 May 2022Circulate the thought paper amongst the Pilot Holistic Review ToR Team members.ICANN org13 May 2022The thought paper has been sent to all ToR team members via email.13 May 2022
37Plenary call #812 May 2022Add weekly Plenary Meeting comments document to the wiki page on a weekly basis.ICANN org19 May 2022Weekly Plenary Meeting comments have been added to their respective wiki pages and will be added weekly moving forward.19 May 2022
38Coordination call #812 May 2022Investigate cause of unreceived ToR team group emails.ICANN org12 May 2022A technical glitch has been identified and resolved. All unreceived emails have been resent.12 May 2022
39Coordination call #812 May 2022Use the approach outlined in the ATRT3 objective C thought paper to revise ToR objectives A, B, C, and D.ICANN org19 May 2022Objectives A, B, C, and D have been revised using the approach outlined in the thought paper.18 May 2022
30Coordination call #628 April 2022Acknowledge and close out the ToR document comments that have been addressed during 5 May Plenary Meeting.ICANN org5 May 2022All addressed ToR document comments have been addressed.23 May 2022
39Plenary call #919 May 2022

Revise the language outlining the process for the assessment of the Pilot Holistic Review so it accurately reflects the Pilot Review team’s participation in the assessment.

ICANN org23 May 2022The ToR language was revised to specify that the deliverable is specific to the Holistic Pilot Review team's assessment.23 May 2022
40Plenary call #919 May 2022

Completed definitions to be moved into definitions section of ToR document.

ICANN org23 May 2022The definitions have been moved into the ToR document.23 May 2022
42Plenary call #919 May 2022Revise ToR document to be consistent with revised objectives and deliverables.ICANN org23 May 2022The ToR was revised in its entirety to be consistent with the revised objectives and deliverables.23 May 2022
43Coordination call #919 May 2022Schedule a debrief session to discuss lessons learned during the Pilot Holistic Review ToR drafting process.ICANN org26 May 2022A debrief session was scheduled for 30 June 2022.19 May 2022
41Plenary call #919 May 2022ToR team members to work over next week to finalize definitions for survey and continuous improvement.Pilot HR ToR team Team members26 May 2022Pilot HR ToR team members provided additional comments and suggestions for these definitions.26 May 2022
44Plenary call #1026 May 2022

Make requested edits to the Pilot Holistic Review ToR document and propose revisions based on Pilot Holistic Review ToR Team comments.

ICANN org31 May 2022All requested edits from the 26 May meeting were made in the ToR document.31 May 2022
47Coordination call #1026 May 2022

Add previously proposed definitions to the ToR section to focus Pilot Holistic ToR Team discussions.

ICANN org27 May 2022The previously proposed definitions were added to the definitions section of the ToR document. 27 May 2022
45Plenary call #1026 May 2022

Pilot Holistic Review ToR Team to continue to work on the ToR definitions over the next week.

Pilot HR ToR Team members2 June 2022Work on ToR definitions was completed.2 June 2022
46Plenary call #1026 May 2022Investigate alternative times to the 9 June plenary call to increase potential attendance.ICANN org2 June 2022Alternative scheduling was investigated but a new time was unable to be secured due to scheduling conflicts.2 June 2022
48Plenary call #112 June 2022Finalize edits to the Pilot Holistic Review ToR based on the ToR team’s comments and the Leads final review.ICANN org and Team Leads15 June 2022The Pilot Holistic Review ToR was finalized as per the Lead's review and proposed edits.15 June 2022
49Plenary call #112 June 2022Send the completed Pilot Holistic Review ToR to the OEC members.ICANN org17 June 2022The Pilot Holistic Review ToR was sent to the OEC members for their review.15 June 2022