DateActivity
June 13Reveal Day - start of 60 day Application Comment Period (ACP)
until end of July 26

get comments from At-Large on the At-Large new gTLD Applications Dashboard Workspace (this would be  Figure 2 of the Procedure to submit comments on and file objections to new gTLDs  )

July 26 - July 27

gTLD RG would review comments on the At-Large new gTLD Applications Dashboard Workspace and decide whether to draft formal comments (this would be Figure 3 of the Procedure to submit comments on and file objections to new gTLDs )

July 26 - August 2

draft of formal comment posted on At-Large new gTLD Applications Dashboard Workspace and worked on by gTLD RG (this would be  Figure 4 of the Procedure to submit comments on and file objections to new gTLDs  )

August 2 to August 10

final comment posted by gTLD RG on August 3 for ALAC's approval (this would be Figure 5 of the Procedure to submit comments on and file objections to new gTLDs )

August 12ACP ends

 

Suggested timetable for gTLD RG during the Objection Period

 

DateActivity
June 13Reveal Day - start of 7 month Objection Period
  
  
  
  
  
January 2013end of Objection Period