- Draft Proposal v. 3.0
- Sidley Austin Post-Istanbul Memo (4 April)
- Sidley Austin Draft Response to Questions/Comments (9 April)
- Design Team Status (2 April)
DT-A (service level expectations) did not submit on 10 April. Expected to complete work by 17 April.Status colour Red title DT-A
DT-B (ccTLD appeals) submitted recommendations to the CWG on 10 April.Status colour Yellow title DT-B
DT-C (customer standing committee) did not submit on 10 April.Status colour Red title DT-C
DT-D (authorization function) has been reviewed by CWG and incorporated into draft v.3.0.Status colour Green title DT-D
DT-E (sac 069) was completed by staff and incorporated into draft v.3.0.Status colour Green title DT-E
DT-F (relationship with RZM) did not submit on 10 April. Expected to complete work by 17 April.Status colour Red title DT-F
DT-G (IANA intellectual property rights) is priority 2 and has not yet been addressed. Chairs to provide update.Status title DT-G
DT-H (.INT) is priority 2 and has not yet been addressed. Chairs to provide update.Status title DT-H
DT-I (competition policy and conflicts of interest) is priority 2 and has not yet been addressed. Chairs to provide update.Status title DT-I
DT-J (confidentiality and conflicts of interest) is priority 2 and has not yet been addressed. Chairs to provide update.Status title DT-J
DT-K (OFAC licensing) is priority 2 and has not yet been addressed. Chairs to provide update.Status title DT-K
DT-L (transition plan) did not submit on 10 April.Status colour Red title DT-L
DT-M (escalation) submitted recommendations to the CWG on 10 April.Status colour Yellow title DT-M
DT-N (periodic review) submitted recommendations to the CWG on 10 April.Status colour Yellow title DT-N
DT-O (budget) submitted recommendations to the CWG on 10 April.Status colour Yellow title DT-O
Red Team has been reassigned as a committee of the whole CWG. See section IV of draft v.3.0 for the outline proposed by staff.Status subtle true title Red Team
...