The key dates identified for the Independent Examiner is: 

ActivityACTIVITYDatesDATES
RFP published22-Apr-14
Participants to indicate interest in submitting RFP30-Apr-14
Participant proposals due by13-May-14
Target for participant presentations (finalists)Week of 19-May-14 (May 19-23)
21 April 2014
Briefing with GNSO (webinar)7 May at 13:00 UTC
GNSO to identify GNSO Review Working Party14 May 2014
Refine examination criteria30 May 2014
Implement 360 assessment15 June 2014Target for Final evaluations and selection of vendor (includes contracting and award to participant)10-Jun-14
Board appointment of independent reviewer26 -Jun-14
Estimated start of implementation01-Jul-14
June 2014
Start of review work1 July 2014
Summary results from 360 Assessment30 July 2014
Draft Report 130 September 2014
Clarification and rebuttal from GNSO11-12 October 2014
Draft Report 231 October 2014
Public comment period1 November 2014 – 5 January 2015
Final Report15 January 2015
Preparation of Implementation Plan16 January – 20 February
Implement Recommendations1 March 2015 – 28 February 2016Final Report15-Jan-15