  1. 10 Aug - Berry - Distribute next version of Public Comment Review Tool - COMPLETED
  2. 20 Aug - Wilson - Make changes to survey tool outline in Review Tool
  3. 20 Aug - Wilson - Activate Survey for Team to review - COMPLETED
  4. 20 Aug - Berry - Determine hosting requirements or ICANN.ORG URL redirect - STARTED

Current Key Milestones:

• Review Comments / Rework draft – August 2012
• Submit to GNSO & release survey for 30 days – 22 August 2012
• Review Survey results – Sept/Oct 2012
• Release Survey results – 30 Oct 2012
• Publish Final Report – 30 Nov 2012