When: Monday, TBD16 FEB, 2012. GMT Standard Time.  2019:00 UTC / This is a 90 Minute Call.

12:00 PSTPDT, 15:00 ESTEDT,  20  20:00 London, 21:00 CET , 0403:00 Beijing

Adobe Connect Link:  http://icann.adobeconnect.com/whoissdt/

...

  1. Berry - 9 MAR - Schedule SO/AC WSWG Roadshow via Webinar (post Costa Rica) - HOLDPENDING
  2. Michael - 5 MAR - Review length of survey, language
  3. Wilson - 10 FEB - Provide examples of survey question types - COMPLETE
  4. Wilson - 5 MAR - Review survey code capability to enable user return to survey for completion at later time - COMPLETE
  5. WSWG Team - 1 MAR - Mold survey questions to available question types - COMPLETE
  6. WSWG Team - 1 MAR - Use of "Question is Relevant " per section/question (review R-6a & R-6b as example)
  7. WSWG Team - 1 MAR - R7/IRD use in survey, Berry to resend to list - STARTEDCOMPLETE
  8. Michael - 5 MAR - Identify editors of survey
  9. Michael - 5 MAR - Identify Test Survey Takers (possible candidates: Don B., Francisco A., Dave P.)

Key Milestones:
• Load survey questions into tool – 29 FEB 2012
• Internal Survey Test Control Group – 3 MAR 2012
• Submit Draft Survey – 5 MAR 2012
• Public comment period – 5 MAR 2012 (42 days min)
• Evangelize SO & ACs, Webinar – MAR 2012, Post Costa Rica
• Rework draft – APR 2012
• Independent review – MAY 2012 - Budget?
• Submit to GNSO & release survey for 30 days – 30 MAY 2012
• Review Survey results – JUL 2012
• Release Survey results – 6 AUG 2012
• Publish Final Report – 1 OCT 2012

Key Milestones:
• Load survey questions into tool – 29 FEB 2012
• Internal Survey Test Control Group – 3 MAR 2012
• Submit Draft Survey – 5 MAR 2012
• Public comment period – 5 MAR 2012 (42 days min)
• Evangelize SO & ACs, Webinar – MAR 2012, Post Costa Rica
• Rework draft – APR 2012
• Independent review – MAY 2012 - Budget?
• Submit to GNSO & release survey for 30 days – 30 MAY 2012
• Review Survey results – JUL 2012
• Release Survey results – 6 AUG 2012
• Publish Final Report – 1 OCT 2012