  • 16 Jun 2022 – Deliver Phase 1A Initial Report on Transfer Policy for public comment, begin Phase 1B deliberations on Change of Registrant
  • 14 Sep 2022 – Conclude review Phase 1A comments
  • 30 Mar 2023 – Deliver Phase 1B Initial Report for public comment
  • 28 Jun 2023 – Conclude review of Phase 1B public comments
  • 16 Aug 2023 – Deliver Phase 1A, 1B Final Report to the GNSO Council
  • Phase 2 is not in scope for this plan, but this process will be repeated when it begins.