Translation and Transliteration of Contact Information Work Plan PDF


Amended Draft Work Plan 2 April 2015

Final Translation and Transliteration of Contact Information PDP WG Work Plan & Timeline (updated 21 February 2014)

 

Target Date

What

Deliverable / Topic for Discussion

Who

19 December 2013

T&T Meeting

-        Inaugural Meeting

All

09 January 2014

T&T WG Meeting

-        Confirmation of Co-Chairs

-        Overview discussion of relevant Charter questions

 

All

16 January  

T&T WG Meeting

-        Assess Work Plan & WG approach

-        Discuss SG/C Input Template & SO / AC outreach message

All

23 January

T&T WG Meeting

-        Finalise Work Plan & WG Approach

-        Finalise SG/C Input Template & SO/AC outreach

All

24 January

Send out SC/C Input Template & SO/AC outreach

 

Staff

30 January

T&T WG Meeting

-        Review Charter Questions

All

6 February

T&T WG Meeting

-        Review Charter Questions

All

13 February

T&T WG Meeting

-        Review Charter Questions

All

20 February

T&T WG Meeting

-        Review Charter Questions

All

21 February

Deadline for SG/C and SO/AC outreach

(Deadline Extended to 31 March)

-        Distribute SO/AC and SG/G Input Review Tool

Staff

27 February

T&T WG Meeting

-        Review Charter Questions in light of SG/C/SO/AC comments

All

6 March

T&T WG Meeting

-        Review Charter Questions in light of SG/C/SO/AC comments

All

13 March

T&T WG Meeting

-        Review Charter Questions in light of SG/C/SO/AC comments

-        Planning for F2F in Singapore

All

22 March

F2F T&T WG Meeting, Singapore

-        Presentation of work accomplished so far

-        Continue to review SG/C/SO/AC comments

All

3 April

T&T WG Meeting

-        Review of F2F Meeting

-        Continue review of SG/C/SO/AC comments

All

10 April

T&T WG Meeting

-        Finalizing review of SG/C/SO/AC comments

All

17 April

T&T WG Meeting

-        Finalizing review of SG/C/SO/AC comments

All

24 April

T&T WG Meeting

-        Stock Take: Where are we, what are the key issues that needs discussion

-        Review of relevant work that is taking place in other relevant efforts

All

01 May

T&T WG Meeting

-        Review of Work Plan

All

08 May

T&T WG Meeting

 

-        Discussion on open issues & development of draft recommendations

All

15 May

T&T WG Meeting

-        Discussion on open issues & development of draft recommendations

All

22 May

T&T WG Meeting

-        Discussion on open issues & development of draft recommendations

All

29 May

T&T WG Meeting

-        Discussion on open issues & development of draft recommendations

All

05 June

T&T WG Meeting

-        Discussion on open issues & development of draft recommendations

All

12 June

T&T WG Meeting

-        Preparation for London F2F Meeting

All

25 June

F2F WG Meeting, London

-        Presentation of Work achieved so far

-        Discussion on open issues & development of draft recommendations

All

3 July

T&T WG Meeting

-        Discussion on open issues & development of draft recommendations

All

10 July

T&T WG Meeting

-        Discussion on open issues & development of draft recommendations

All

17 July

T&T WG Meeting

-        Continue review of comments received

All

24 July

T&T WG Meeting

-        Continue review of comments received

All

31 July

T&T WG Meeting

-        Continue review of comments received

All

7 August

T&T WG Meeting

-        Continue review of comments received

All

14 August

T&T WG Meeting

-        Continue review of comments received

All

21 August

T&T WG Meeting

-        Continue review of comments received

All

28 August

T&T WG Meeting

-        Continue deliberations on open issues identified in the Initial Report

-        Schedule / Work plan check point

All

4 September

T&T WG Meeting

-        Continue deliberations on open issues identified in the Initial Report

 

All

11 September

T&T WG Meeting

-        Finalising and Submitting Initial Report

Staff

12 September

Opening Public Comment

-        Submitting announcement to relevant websites, mailing lists, etc.

Staff

15 September

T&T WG Meeting

-        Deadline for Initial Report to be submitted for Los Angeles ICANN Meeting

All / Staff

25 September

T&T WG Meeting

-        Preparation for Los Angeles F2F Meeting

All

02 October

T&T WG Meeting

-        Preparation for Los Angeles F2F Meeting

All

15 October

F2F WG Meeting, Los Angeles

-        Presentation of Initial Report

-        Discussing with Community

All

24 October

Closing Public Comment

-        Staff Prepare Public Comment Review Tool and Distributes to WG

Staff

30 October

T&T WG Meeting

-        Review of Public Comments

All

06 November

T&T WG Meeting

-        Review of Public Comments

All

13 November

T&T WG Meeting

-        Review of Public Comments

All

20 November

T&T WG Meeting

-        Review of Public Comments and Preparing Final Report

All/Staff

27 November

T&T WG Meeting

-        Review of Public Comments and Preparing Final Report

All/Staff

01 December

Deadline to Submit Motion for 11 December GNSO Council Meeting

 

 

 

 

 