Status Report

Date - August 8, 2008

Summary Status

Are there review and approval problems? Yes
Will target dates be missed? Yes
Are there scope changes? Yes
Are there estimate problems? Yes
Are there technical problems? No
Are there resource problems? Yes

Accomplishments this week

  • Reviewed and revised near-term approach and schedule

Plans for next week

  • Launch email-summarizing effort
  • Enjoy a late-August break from Fast Flux

Issues and concerns

  • No labels